Question

1 Approved Answer

Overhead costs allocated and apportioned are 3 2 , 9 0 0 , 4 2 , 7 5 0 and 1 4 , 0 0

Overhead costs allocated and apportioned are 32,900,42,750 and 14,000 for centres A, B & C, respectively. Overheads in cost centre C are reapportioned to the Production cost centres A and B in 80% and 20% in B.Machine hours in cost centre A are 2500. The OAR in cost centre B is 10.00 per machine hour. actual information for the same period is that overhead cost incurred in cost centre A including the reapportionment is 37,920.Machine hours worked are in A -2670, B-3225. Overheads were over-absorbed in cost centre B by 1,800.
Required : For cost centre A find the budgeted overhead absorption rate for the period and the over or under-absorption of overheads for the period.
For cost centre B, find the budgeted OAR and the actual OAR for the period.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

Define epistemology.

Answered: 1 week ago