Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Overview The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction must start July 1, 2021, and
Overview The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction must start July 1, 2021, and be completed in time for the start of the 2024 season. A penalty clause of $100,000 per day of delay beyond May 20, 2024, is written into the contract. Ben Keith, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $2 million on the project. He also said if they are successful, the prospects for future projects are quite good since there is a projected renaissance in building classic ball parks with modern luxury boxes. QUESTIONS Given the information provided in Table 6.3, construct a Pert Diagram using ProjectLibre, Microsoft Project or Microsoft Word for the stadium project and answer the following questions: 1. Will the project be able to be completed by the May 20 deadline? How long will it take? 2. What is the critical path for the project? 3. Based on the schedule would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule. ID Duration TABLE 6.3 Greendale Stadium Case Predecessors) INN 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Activity Baseball Stadium Clear stadium site Demolish building Set up construction site Drive support piling Pour lower concrete bowl Pour main concourse Install playing field Construct upper steel bowl Install seats Build luxury boxes Install jumbotron Stadium infrastructure Construct steel canopy Light installation Build roof supports Construct roof Install roof tracks Install roof Inspection 70 days 30 days 70 days 120 days 120 days 120 days 90 days 120 days 140 days 90 days 30 days 120 days 75 days 30 days 90 days 180 days 90 days 90 days 20 days 5 3,6 3,6 3,6 7,9 7,9 7,9 7,9 10 14 6 16 16 17,18 8,11,13,15,19 Submit a word document with your answers to the questions above. Provide appropriate screenshots. Also upload the Project File. Overview The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction must start July 1, 2021, and be completed in time for the start of the 2024 season. A penalty clause of $100,000 per day of delay beyond May 20, 2024, is written into the contract. Ben Keith, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $2 million on the project. He also said if they are successful, the prospects for future projects are quite good since there is a projected renaissance in building classic ball parks with modern luxury boxes. QUESTIONS Given the information provided in Table 6.3, construct a Pert Diagram using ProjectLibre, Microsoft Project or Microsoft Word for the stadium project and answer the following questions: 1. Will the project be able to be completed by the May 20 deadline? How long will it take? 2. What is the critical path for the project? 3. Based on the schedule would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule. ID Duration TABLE 6.3 Greendale Stadium Case Predecessors) INN 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Activity Baseball Stadium Clear stadium site Demolish building Set up construction site Drive support piling Pour lower concrete bowl Pour main concourse Install playing field Construct upper steel bowl Install seats Build luxury boxes Install jumbotron Stadium infrastructure Construct steel canopy Light installation Build roof supports Construct roof Install roof tracks Install roof Inspection 70 days 30 days 70 days 120 days 120 days 120 days 90 days 120 days 140 days 90 days 30 days 120 days 75 days 30 days 90 days 180 days 90 days 90 days 20 days 5 3,6 3,6 3,6 7,9 7,9 7,9 7,9 10 14 6 16 16 17,18 8,11,13,15,19 Submit a word document with your answers to the questions above. Provide appropriate screenshots. Also upload the Project File
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started