Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

P 1 1 - 3 Draw CPM diagram and determine critical path A project consists of the following activities. table [ [ Activity ,

P11-3 Draw CPM diagram and determine critical path A project consists of the following activities.
\table[[Activity,Duration (days)],[A,3],[B,5],[C,7],[D,5],[E,4],[F,6],[G,2],[H,3]]
A and B can be commenced concurrently. Both C and D can be commenced after completion of A. E cannot commence until both B and C have been completed. F can commence after completion of B. G cannot commence until D and E have been completed. H follows completion of F.
Required:
(a) Draw the network diagram.
(b) List the paths in the network and identify the critical path.
(c) What is the total project completion time?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Accounting

Authors: Joe Hoyle, Thomas Schaefer, Timothy Doupnik

10th edition

0-07-794127-6, 978-0-07-79412, 978-0077431808

Students also viewed these Accounting questions