Question

1 Approved Answer

P 1 has a production rate of 1 5 units / hour , P 2 = 3 0 units / hour , P 3 =

P1 has a production rate of 15units/hour, P2=30units/hour, P3=10 units per hour, P4=4units/hour, P5=1unit(s) per hour for each P5 and P6=5 units per hour.
Operation P4 occurs seperately from and simultaneously with operations P1-P3.
Operation P5 has three parallel and identical lines; therefore, each part only needs to go through one of the three lines.
a) The bottleneck of this system is station P
enter your response here.
b) The bottleneck time of the system is
enter your response here minutes per unit.
c) The throughput time is
enter your response here minutes per unit.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: William J. Stevenson

13th edition

1259667472, 978-1259667473

More Books

Students also viewed these General Management questions