P 8-28 (similar to) Question Help You are choosing between two projects. The cash flows for the projects are given in the following table (5
P 8-28 (similar to) Question Help You are choosing between two projects. The cash flows for the projects are given in the following table (5 million): Project Year 0 - $48 - $101 Year 1 $23 $19 Year 2 $22 $42 Year 3 $22 $51 Year 4 $17 $58 B a. What are the IRRs of the two projects? b. If your discount rate is 5.3%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently