Question
P1. A company needs to manage a project, which consists of the following set of activities: Task Duration I.P.s A 1 - B 4 A
P1. A company needs to manage a project, which consists of the following set of activities:
Task
Duration
I.P.s
A
1
-
B
4
A
C
3
B
D
3
C
E
2
B
F
4
E
G
2
D, F
Construct a network diagram for this project. What are all possible paths for this project? List the paths as: A-B-C... What is the critical path(s)? How long will it take to complete this project?
P2. Assume that the following project has the same IPs as in the problem above.
Activity
Normal
Crash
Normal
Crash
Slope
A
5
3
$6,000.00
$8,000.00
$1,000.00
B
3
2
$18,000.00
$19,000.00
$1,000.00
C
4
2
$14,000.00
$19,000.00
$2,500.00
D
7
4
$6,000.00
$9,000.00
$1,000.00
E
6
1
$9,000.00
$14,000.00
$1,000.00
F
5
3
$12,000.00
$14,000.00
$1,000.00
G
4
2
$3,500.00
$7,500.00
$2,000.00
What would be the critical time?
If it is possible to crash the project to 1 less than the critical time (e.g., 19 CT crashed to 18), what are all the possible ways to do that with the minimum increase in cost? Be sure to support your answer with a brief explanation.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started