Question

1 Approved Answer

* P18-11 (Long-Term Contract with Interim Loss) On March 1, 2014, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for

* P18-11 (Long-Term Contract with Interim Loss) On March 1, 2014, Pechstein Construction Company
contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of
$8,400,000. The building was completed by October 31, 2016. The annual contract costs incurred, estimated
costs to complete the contract, and accumulated billings to Fabrik for 2014, 2015, and 2016 are given below.
2014 2015 2016
Contract costs incurred during the year $ 2,880,000 $ 2,230,000 $ 2,190,000
Estimated costs to complete the contract at 12/31 3,520,000 2,190,000 0
Billings to Fabrik during the year 3,200,000 3,500,000 1,700,000
Instructions
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be
recognized as a result of this contract for the years ended December 31, 2014, 2015, and 2016. (Ignore
income taxes.)
(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized
as a result of this contract for the years ended December 31, 2014, 2015, and 2016. (Ignore
incomes taxes.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Principles And Techniques

Authors: Sanjib Kumar Basu, Andrei Alexandrescu

1st Edition

8177581783, 9788177581782

More Books

Students also viewed these Accounting questions