Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

PA 8 - 4 ( Algo ) In the welding operations of a bicycle manufacturer... In the welding operations of a bicycle manufacturer, a bike

PA 8-4(Algo) In the welding operations of a bicycle manufacturer...
In the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 13.6 hours. The time in the welding operation
is spent as follows: 3 hours waiting in front of the cutting machine for the batch to start, 3 hours waiting for the setup of the machine, 1
hour waiting for the other pieces of the batch to go through cutting, 2 minutes at the cutting machine, and 3 hours waiting for the
transfer to the welding machine. Then, at the welding machine, the unit spends 1 hour waiting in front of the welding machine for the
batch to start, 1 hour waiting for the setup of the welding machine, 0.6 hours waiting for the other pieces of the batch to go through
welding, 0.65 minutes at the welding machine, and 1 hour waiting for the transfer to the next department.
Determine the exact flow time. What is the value-added percentage of the flow time?
Note: Round your percentage answer to 4 decimal places.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Time Management

Authors: Patrick Forsyth

4th Edition

0749475811, 978-0749475819

More Books

Students also viewed these General Management questions

Question

What is the distribution of B(s) + B(t), s t?

Answered: 1 week ago