Paragraph Styles You have a project to be completed in 12 months and the budget of the project is 100,000 USD. 6 months have
Paragraph Styles You have a project to be completed in 12 months and the budget of the project is 100,000 USD. 6 months have passed and 60,000 USD has been spent, but on a closer review, you find that only 50% of the work has been completed. a) Find the project's Schedule Variance (SV) and determine if you are ahead of schedule or behind schedule. (2.5 points) b) Find the project's Cost Variance (CV) and determine if you are under budget or over budget. (2.5 points) Editina