PART 1) Which of the following statements(s) is/are correct? Group of answer choices An weakness of SPI is that it does not take into account
PART 1)
Which of the following statements(s) is/are correct?
Group of answer choices
An weakness of SPI is that it does not take into account if the project's critical path is on schedule. It is possible to have a SPI greater than 1.0 while the project is actually behind schedule.
An weakness of SPI is that it does not take into account of activites/tasks that have a budgeted cost of zero, such as tasks dealing with submittals and ordering of materials.
SPI should always be used together with the critical path to determine a project's schedule performance.
SPI alone is a reliable indicator on the schedule performance of a project.
PART 2)
The Actual Cost of the Work Performed (ACWP) is obtained from the cost-loaded schedule.
Group of answer choices
true
false
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started