Question

1 Approved Answer

PART 1) Which of the following statements(s) is/are correct? Group of answer choices An weakness of SPI is that it does not take into account

PART 1)

Which of the following statements(s) is/are correct?

Group of answer choices

An weakness of SPI is that it does not take into account if the project's critical path is on schedule. It is possible to have a SPI greater than 1.0 while the project is actually behind schedule.

An weakness of SPI is that it does not take into account of activites/tasks that have a budgeted cost of zero, such as tasks dealing with submittals and ordering of materials.

SPI should always be used together with the critical path to determine a project's schedule performance.

SPI alone is a reliable indicator on the schedule performance of a project.

PART 2)

The Actual Cost of the Work Performed (ACWP) is obtained from the cost-loaded schedule.

Group of answer choices

true

false

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles Of Financial Modelling Model Design And Best Practices Using Excel And VBA

Authors: Michael Rees

1st Edition

111890401X, 978-1118904015

More Books

Students also viewed these Finance questions

Question

Drag the boxes to match the ansv -8+8=0

Answered: 1 week ago

Question

Explain how to reward individual and team performance.

Answered: 1 week ago