Question
Part 2 The average tardiness (job lateness) for the sequence developed using the FCFS rule = Average job lateness=Total late daysNumber of jobs = days
Part 2
The average tardiness (job lateness) for the sequence developed using the FCFS rule =
Average job lateness=Total late daysNumber of jobs
=
days (round your response to two decimal places).
Part 3
The percentage utilization for the sequence developed using the FCFS rule =
Utilization=Total job work (processing) timeSum of total flow time
=
(enter your response as a percentage rounded to two decimal places).
Part 4
The average completion time (flow time) for the sequence developed using the FCFS rule =
Average completion time=Sum of total flow time Number of jobs
=
days (round your response to two decimal places).
Part 5
The average number of jobs in the system for the sequence developed using the FCFS rule =
Average number of jobs in system=Sum of total flow timeTotal job work (processing) time
=
jobs (round your response to two decimal places).
Part 6
Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received):
Under the EDD rule, jobs are scheduled in the order in which they due. Arrange the due dates in ascending order to perform the scheduling. The ordered due dates are
The average tardiness (job lateness) for the sequence developed using the EDD rule =
days (round your response to two decimal places).
Part 8
The percentage utilization for the sequence developed using the EDD rule =
(enter your response as a percentage rounded to two decimal places).
Part 9
The average completion time (flow time) for the sequence developed using the EDD rule =
Average completion time=Sum of total flow time Number of jobs
=
days (round your response to two decimal places).
Part 10
The average number of jobs in the system for the sequence developed using the EDD rule =
Average number of jobs in system=Sum of total flow timeTotal job work (processing) time
=
jobs (round your response to two decimal places).
Part 11
Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received):
Under the SPT rule, jobs are scheduled based on the ordering of the processing time with the shortest one first. Arrange the processing times in ascending order to perform the scheduling. The ordered processing times are
Part 12
The average tardiness (job lateness) for the sequence developed using the SPT rule =
days (round your response to two decimal places).
Part 13
The percentage utilization for the sequence developed using the SPT rule =
(enter your response as a percentage rounded to two decimal places).
Part 14
The average completion time (flow time) for the sequence developed using the SPT rule =
Average completion time=Sum of total flow time Number of jobs
=
days (round your response to two decimal places).
Part 15
The average number of jobs in the system for the sequence developed using the SPT rule =
Average number of jobs in system=Sum of total flow timeTotal job work (processing) time
=
jobs (round your response to two decimal places).
Part 16
Using the LPT (longest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received):
Under the LPT rule, jobs are scheduled based on the ordering of the processing time with the longest one first. Arrange the processing times in descending order to perform the scheduling. The ordered processing times are
Part 17
The average tardiness (job lateness) for the sequence developed using the LPT rule =
Average job lateness=Total late daysNumber of jobs
=
days (round your response to two decimal places).
Part 18
The percentage utilization for the sequence developed using the LPT rule =
Utilization=Total job work (processing) timeSum of total flow time
=
(enter your response as a percentage rounded to two decimal places).
Part 19
The average completion time (flow time) for the sequence developed using the LPT rule =
Average completion time=Sum of total flow time Number of jobs
=
days (round your response to two decimal places).
Part 20
The average number of jobs in the system for the sequence developed using the LPT rule =
Average number of jobs in system=Sum of total flow timeTotal job work (processing) time
=
jobs (round your response to two decimal places).
Part 21
Critical Ratio (CR) for each job is given by the relationship:
CR=Due DateDate TodayProcessing Time.
Based on the given information, the CR for Job
A
=
(round your response to two decimal places).
Part 22
CR for Job
B
=
(round your response to two decimal places).
Part 23
CR for Job
C
=
(round your response to two decimal places).
Part 24
CR for Job
D
=
(round your response to two decimal places).
Part 25
CR for Job
E
=
(round your response to two decimal places).
a) Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order An Alabama lumberyard has four jobs on order, as shown in the following table. Today is is (assume that jobs came in the order in which they are listed in the table): day 205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: All dates are specified as manufacturing planning calendar days. Assume that all jobs The average tardiness (job lateness) for the sequence developed using the FCFS rule = days arrive on day 205 . Compute all times based on initiating work on day 205 . (round your response to two decimal places)Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started