Part B & C The following activities are part of a project to be scheduled using CPM: IMMEDIATE PREDECESSOR ACTIVITY A TIME (WEEKS) 7 DU
Part B & C
The following activities are part of a project to be scheduled using CPM: IMMEDIATE PREDECESSOR ACTIVITY A TIME (WEEKS) 7 DU D E F G A A C BD D EF 5 4 8 a. What is the critical path? O A-B-D-F-G O A-B-E-G O A-C-D-E-G O A-C-D-F-G b. How many weeks will it take to complete the project? Number of weeks c. How much slack does activity B have? Slack of activity B weeks Step by Step Solution