Part IV Job-Order Costing (27 marks) 1. Faster Company uses a job-order cost system in each of its two manufacturing departments. Manufacturing overhead is applied
Part IV Job-Order Costing (27 marks) 1. Faster Company uses a job-order cost system in each of its two manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labour cost in Department A, and machine hours in Department B. Than callousina setimatec wore made for the year: a. Calculate the predetermined overhead rate for each department. ( 4 marks)