parts A through E please
Save Homework: Homework Set 4 Score: 0 of 2 pts P11-19 (similar to) 15 of 25 (16 complete) HW Score: 54%, 27 of 50 p Question Help Breakeven cash inflows and risk Boardman Gases and Chemicals is a supplier of highly purified gases to semiconductor manufacturers. A large chip producer has asked Boardman to build a new gas production facility close to an existing semiconductor plant. Once the new gas plant is in place, Boardman will be the exclusive supplier for that semiconductor fabrication plant for the subsequent 10 years. Boardman is considering one of two plant designs. The first is Boardman's "standard plant which will cost $38.6 million to build. The second is for a "custom" plant which will cost $54.3 million to build. The custom plant will allow Boardman to produce the highly specialized gases required for an emergency semiconductor manufacturing process. Boardman estimates that its client will order $12.3 million of product per year if the standard plant is constructed, but if the custom design is put in place, Boardman expects to sell $18.3 million worth of product annually to its client Boardman has enough money to build either type of plant, and, in the absence of risk differences, accepts the project with the highest NPV. The cost of capital is 17 2%. a. Find the NPV for each project. Are the projects acceptable? b. Find the breakeven cash inflow for each project C. The firm has estimated the probabilities of achieving various ranges of cash inflows for the two projects, as shown in the table !! What is the probability that each project will achieve the breakeven cash inflow found in part (b)? hinh net ir m ari h ich nennet hen the natantinhhinha Mic in the vil trods af of the hun ninete a. The NPV for project standard" is $ (Round to the nearest cent) 11-19 (similar to) Question Help exclusive suppiler for at semiconductor Tancation plant for the subsequent 10 years. Boaraman is considering one or two piant designs. I ne mistis Boaraman standard plant which will cost $38.6 million to build. The second is for a "custom" plant which will cost $54.3 million to build. The custom plant will allow Boardm to produce the highly specialized gases required for an emergency semiconductor manufacturing process. Boardman estimates that its client will order $12.3 mill of product per year if the standard plant is constructed, but if the custom design is put in place, Boardman expects to sell $18.3 million worth of product annually its client Boardman has enough money to build either type of plant, and, in the absence of risk differences, accepts the project with the highest NPV. The cost of capital is 17.2% a. Find the NPV for each project. Are the projects acceptable? b. Find the breakeven cash inflow for each project. C. The firm has estimated the probabilities of achieving various ranges of cash inflows for the two projects, as shown in the table . What is the probability thar each project will achieve the breakeven cash inflow found in part (b)? d. Which project is more risky? Which project has the potentially higher NPV? Discuss the risk-return trade-offs of the two projects. e. If the firm wished to minimize losses (that is, NPV