Payton Corporation had decided to respond to a government RFP for the R&D phase on a new project. The statement of work specified that the

Payton Corporation had decided to respond to a government RFP for the R&D phase on a new project. The statement of work specified that the project must be completed within ninety days after go-ahead, and that the contract would be at a fixed cost and fee. The majority of the work would be accomplished by the development lab. According to government regulations, the estimated cost must be based on the average cost of the entire department, which was $19.00 per hour (unburdened). Payton won the contract for a total package (cost plus fee) of $305,000. After the first weekly labor report was analyzed, it became evident that the development lab was spending $28.50 per hour. The project manager decided to discuss the problem with the manager of the development lab. Project manager: "Obviously you know why I'm here. At the rate that you're spending money, we'll overrun our budget by 50 percent." Lab manager: "That's your problem, not mine. When I estimate the cost to do a job, I submit only the hours necessary based on historical standards. The pricing department converts the hours to dollars based on department averages." Project manager: "Well, why are we using the most expensive people? Obviously there must be lower-salaried people capable of performing the work. Lab manager: "Yes, I do have lower-salaried people, but none who can complete the job within the two months required by the contract. I have to use people high on the learning curve, and they're not cheap. You should have told the pricing department to increase the average cost for the department." Project manager: "I wish I could, but government regulations forbid this. If we were ever audited, or if this proposal were compared to other salary structures in other proposals, we would be in deep trouble. The only legal way to accomplish this would be to set up a new department for those higher-paid employees working on this project. Then the average department salary would be correct. "Unfortunately the administrative costs of setting up a temporary unit for only two months is prohibitive. For long-duration projects, this technique is often employed. "Why couldn't you have increased the hours to compensate for the increased dollars required?" Lab manager: "I have to submit labour justifications for all hours I estimate. If I were to get audited, my job would be on the line. Remember, we had to submit labour justification for all work as part of the proposal.

"Perhaps next time management might think twice before bidding on a short duration project. You might try talking to the customer to get his opinion." Project manager: "His response would probably be the same regardless of whether I explained the situation to him before we submitted the proposal or now, after we have negotiated it. There's a good chance that l've just lost my Christmas bonus."

image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology Project Management

Authors: Kathy Schwalbe

9th Edition

1337101354, 978-1337101356

More Books

Students also viewed these General Management questions

Question

How we can improve our listening skills?

Answered: 1 week ago

Question

How do artifacts affect interaction between members of the team?

Answered: 1 week ago