Jenny Thompson Construction Company has entered into a contract beginning January 1, 2007, to build a parking
Question:
Jenny Thompson Construction Company has entered into a contract beginning January 1, 2007, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period.
Instructions
(a) Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period.
(b) Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the constructionperiod.