PDOT has contracted for new electronic signage for Pacifica highways. The project is for 200 signs to be built in 24 months for $2 million.
- PDOT has contracted for new electronic signage for Pacifica highways. The project is for 200 signs to be built in 24 months for $2 million. After 6 months, 25 signs have been completed and $500,000 has been spent:
- Calculate the following: (36 pts)
- What is the BAC?
- What is the PV?
- What is the EV?
- What is the AC?
- What is the SV?
- What is the CV?
- What is the SPI?
- What is the CPI?
- What is the EAC (cost)?
- Assess the situation of the VDOT signage project. Provide reasons for your assessment? If the project is in trouble, what needs to be done to get it back on track? (9 pts)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started