Penner Builders contracted to build a high-rise for $28,000,000. Construction began in 2014 and is expected to be completed in 2017. Data for 2014 and
Penner Builders contracted to build a high-rise for $28,000,000. Construction began in 2014 and is expected to be completed in 2017. Data for 2014 and 2015 are:
2014 2015
Costs incurred to date $3,600,000 $10,400,000
Estimated costs to complete 14,400,000 9,600,000
Penner uses the percentage-of-completion method.
Instructions
(a) How much gross profit should be reported for 2014? Show your computation.
(b) How much gross profit should be reported for 2015? Show your computation.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started