Perform the Critical Path Method (CPM) analysis for the project. From the information in Table 2, draw the CPM network and calculate the free float
- Perform the Critical Path Method (CPM) analysis for the project. From the information in Table 2, draw the CPM network and calculate the free float if available. The project has 9 activities and has to be completed in 24 months. Decide the duration (in month) for each of the activities.
Table 2/Jadual 2
ID | Activity/Aktiviti | Preceeding Activity (IPA) / Aktiviti Mendahului | Duration/Tempoh (month/bulan) |
A | Site clearing | - | |
B | Mobilization | A | |
C | Earthwork | B | |
D | Piling | C | |
E | Foundation | D | |
F | Superstructure | E | |
G | Architecture Finishing | F | |
H | M&E work | F | |
I | Commissioning | G, H |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started