Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow: Direct Labor-Hours per unit Annual Production Rims 0.30 26,000
Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow:
Direct Labor-Hours per unit | Annual Production | |
Rims | 0.30 | 26,000 units |
Posts | 0.50 | 70,000 units |
Additional information about the company follows:
- Rims require $15 in direct materials per unit, and Posts require $11.
- The direct labor wage rate is $15 per hour.
- Rims are more complex to manufacture than Posts and they require special equipment.
- The ABC system has the following activity cost pools:
Estimated Activity | ||||||
Activity Cost Pool | Activity Measure | Estimated Overhead Cost | Rims | Posts | Total | |
Machine setups | Number of setups | $ | 32,900 | 60 | 140 | 200 |
Special processing | Machine-hours | $ | 114,800 | 4,000 | 0 | 4,000 |
General factory | Direct labor-hours | $ | 1,404,000 | 6,000 | 72,000 | 78,000 |
1. Compute the activity rate for each activity cost pool. (Round your answers to 2 decimal places.)
Machine setups: ____ per setup
Special processing: ____ per MH
General factory: _____ per DLH
1 Required information [The following information applies to the questions displayed below! Performance Products Corporation makes two products, titanium Rims and Posts Data regarding the tw rect Labor Hours per unit 0.30 0.50 Rias Posts let Production 26,990 units 70,000 units Additional information about the company follows: a. Rims require $15 in direct materials per unit, and Posts require $11 b. The direct labor wage rate is $15 per hout c. Rims are more complex to manufacture than Posts and they require special equipment d. The ABC system has the following activity cost pools Estate Activity Activity cost. Pool Machine setups Special processing General factory Activity Measure Number of setups Machinhos Direct Isbeehours Estimated Overhead Cott $ 32,900 $ 114,000 31.404,000 4.000 0.000 Posts 140 e 72,000 Total 200 4.000 78,000 Required: 1. Compute the activity rate for each activity cost pool (Round your answers to 2 decimal places.) Activity Cout. Pool Activity Rate Machines pers Special processing General factory per MH DW DUHStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started