Question
Performance Products Corporation makes two products, Titanium Rims and Posts. Data regarding the two products is provided in the following table: Direct Labor Hours per
Performance Products Corporation makes two products, Titanium Rims and Posts. Data regarding the two products is provided in the following table:
| Direct Labor Hours per Unit | Annual Production |
Rims | 0.40 | 20,000 units |
Posts | 0.20 | 80,000 units |
Additional information about the company follows:
- Rims require $17.00 in direct materials per unit, and Posts require $10.00.
- The direct labor wage rate is $16.00 per hour.
- Rims are more complex to manufacture than Posts, and they require special equipment.
- The Activity Based Costing (ABC) System has the following activity cost pools:
Activity Cost Pool | Activity Measure | Estimated Overhead Cost | Rims | Posts | Total Activity for Rims and Posts |
Machine Setups
|
Number of Machine Setups |
$21,600 |
100 |
80 |
180 |
Special Processing
|
Machine Hours |
$180,000 |
4,000 |
0 |
4,000 |
General Factory
|
Direct Labor Hours |
$288,000 |
8,000 |
16,000 |
24,000 |
- Determine the amount of manufacturing overhead assigned to each product (Rims and Posts) for each activity cost pool. - Please show your work so that I can better understand the answer :)
Overhead is assigned to the two products as follows:
Rims:
Activity Cost Pool
Activity Rate
Activity
ABC Cost
Machine Setups
Special Processing
General Factory
Total Factory Overhead
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started