Perot Corporation is developing a new CPU chip based on a new type of technology. Its new chip, the Patay2 chip, will take two years

Perot Corporation is developing a new CPU chip based on a new type of technology. Its new chip, the Patay2 chip, will take two years to develop. However, because other chip manufacturers will be able to copy the technology, it will have a market life of two years after it is introduced. Perot expects to be able to price the chip higher in the first year, and it anticipates a significant production cost reduction after the first year as well. The relevant information for developing and selling the Patay2 is given as follows:

PATAY2 CHIP PRODUCT ESTIMATES
Development cost $ 20,000,000
Pilot testing $ 5,000,000
Debug $ 3,500,000
Ramp-up cost $ 3,000,000
Advance marketing $ 6,000,000
Marketing and support cost $ 1,000,000 per year
Unit production cost year 1 $ 655.00
Unit production cost year 2 $ 545.00
Unit price year 1 $ 820.00
Unit price year 2 $ 650.00
Sales and production volume year 1 250,000
Sales and production volume year 2 150,000
Interest rate 10 %

Assume all cash flows occur at the end of each period.

a. What is the net present value (at the discount rate of 10%) of this project? (Negative value should be indicated by a minus sign. Enter your answer in thousands of dollars. Round your answer to the nearest thousand.)

Net Present Value:

b. Perots engineers have determined that spending $10 million more on development will allow them to add even more advanced features. Having a more advanced chip will allow them to price the chip $50 higher in both years ($870 for year 1 and $700 for year 2). What is the NPV of the project if this option is implemented? (Negative value should be indicated by a minus sign. Enter your answer in thousands of dollars. Round your answer to the nearest thousand.)

Net Present Value:

c. If sales are only 200,000 the first year and 100,000 the second year, what would the NPV of the project be? Assume the development costs and sales price are as originally estimated. (Negative value should be indicated by a minus sign. Enter your answer in thousands of dollars. Round your answer to the nearest thousand.)

Net Present Value:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Finance For Non Financial Managers

Authors: Pierre Bergeron

6th Edition

0176501630, 9780176501631

More Books

Students also viewed these Finance questions

Question

1. What causes musculoskeletal pain?

Answered: 1 week ago