Pieter's project has had uncontrolled growth of the project scope resulting from incremental change to requirements without consideration of the impact on resources or schedules.
Pieter's project has had uncontrolled growth of the project scope resulting from incremental change to requirements without consideration of the impact on resources or schedules. Pieter has experienced:
WBS Expansion
Scope Aggregation
Scope Creep
Decompensatory Scope