Question
Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. Given the project table
Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. Given the project table below calculate the crash cost for 8 hours of time-savings. Suppose Pirmin calls the customer and asks for a project extension, reducing the amount of time he needs to crash.
Activity | Normal Duration (hours) | Normal Cost ($) | Crash Duration (hours) | Crash Cost ($) | Immediate Predecessors |
A | 2 | 10 | 2 | 50 | - |
B | 3 | 15 | 2 | 23 | A |
C | 5 | 25 | 4 | 30 | B |
D | 3 | 20 | 1 | 24 | C |
E | 6 | 30 | 4 | 45 | C |
F | 1 | 5 | 1 | 50 | C,E |
G | 7 | 35 | 6 | 50 | F |
H | 10 | 50 | 7 | 80 | D,G |
a. What is the critical path? [ Select ] ["A,B,C,E,F,G,H", "A,B,C,D,E,F,G,H", "A,B,C,D,H", "A,B,C,F,G,H"]
b. What is the project length? [ Select ] ["23 hours", "15 hours", "34 Hours", "35 hours"]
c. Which activity should the bike shop crash first [ Select ] ["C", "B", "E", "D"] , and how much would it add to the project cost? [ Select ] ["$7.50", "$10", "$2", "$5"]
d. Which activity should be crashed next to reduce an additional hour off the project [ Select ] ["D", "C", "E", "NONE"] , and what would be the total cost? (reducing the project by 2 hours) [ Select ] ["$15.75", "$12.50", "$14.50", "$5"]
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started