Question
Planned Value WBS Element (PV) 2.01 Airframe 48000 Earned Value Actual Cost (EV) (AC) 48000 50000 2.02 Engines 22000 21000 23000 2.03 Avionics 80000
Planned Value WBS Element (PV) 2.01 Airframe 48000 Earned Value Actual Cost (EV) (AC) 48000 50000 2.02 Engines 22000 21000 23000 2.03 Avionics 80000 60000 45000 2.04 Communications 30000 30000 30000 2.05 Tech. Manuals 42000 42000 48000 2.06 Spares 40000 35000 42000 2.07 Training 80000 Project Total 342000 80000 86000 316000 Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report (October 31, 20XX) 324000 Consider the project performance report presented in figure 14.1. As a project manager, these results should lead you to...
Step by Step Solution
There are 3 Steps involved in it