Please anser questions attached, I dont need explanations. The following six jobs are to be scheduled on a single machine: Job 1 2 3 4

Please anser questions attached, I dont need explanations.

The following six jobs are to be scheduled on a single machine:

Job 1 2 3 4 5 6
Processing time (min.) 100 130 210 70 150 110
  1. Suppose the jobs are processed in FCFS numerical order. Compute the makespan, flow time for each job, and overall average flow time. Round your answers to the nearest whole number.
Job Flow Time (min)
1
2
3
4
5
6

1. What are the Makespan in minutes?

2. what are the Average flow time in minutes?

3. In what order would the jobs be processed using the SPT rule? What is the SPT sequence?

4. Compute the average flow time after each job is completed. Round your answer to the nearest whole number.

(Average flow time in minutes)

5. Compare this answer with your answer in question 2. Does the SPT rule or numerical order minimizes flow time and gets the most work done in the least amount of time?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Marketing

Authors: Nigel Piercy and David Cravens

10th edition

78028906, 978-0078028908

More Books

Students also viewed these General Management questions

Question

What research background do you have?

Answered: 1 week ago

Question

Find the median for the set of measurements 2, 9, 11, 5, 6, 27.

Answered: 1 week ago

Question

Find the median for the set of measurements 2, 9, 11, 5, 6.

Answered: 1 week ago