Please answer 10, 12, 13, 14,15,16,17
10. Determine the estimated cost of the work performed each week given the tasks-with their associated costs and schedules-shown in Table 7-30 When a task spans more than one week, the costs should be divided equally among the weeks. Table 7-3 Data for Problem 100 Week Task Cost ($) Start Finish Mobilization 1,000 Grubbing 4,000 Rough Excavate Roadway 24,000 2 Grade and Roll Sub Grade 1,000 Place and Compact Road Base 8,000 Place and Compact Asphalt 12,000 Grade Shoulders 1,000 Clean Up 1,000 Demobilize 1,000 6 12. A project consists of three tasks. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 3. Task B is scheduled to begin at the start of Week 1 and finish at the end of Week 2. Task C is scheduled to begin at the start of Week 2 and end at the end of Week 3. The budgeted cost for Task A is $22,000, for Task B is $17,000, and for Task C is $15,000. At the end of the second week, Task A is 65% complete, Task B is 95% complete, and Task C is 60% complete. What is the SPI for the project at the end of the second week? 13. A project consists of six tasks. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 4. Task B is scheduled to begin at the start of Week 1 and finish at the end of Week 2. Task C is scheduled to begin at the start of Week 3 and end at the end of Week 4. Task D is scheduled to begin at the start of Week 1 and end at the end of Week 1. Task E is scheduled to begin at the start of Week 2 and end at the end of Week 4. Task F is scheduled to begin at the start of Week 4 and end at the end of Week 4. The budgeted cost for Task A is $10,000, for Task B is $2,000, for Task C is $3,000, for Task D is $1,000, for Task E is $6,000, and for Task F is $4,000. At the end of the third week, Task A is 80% complete, Task B is 100% complete, Task C is 40% complete, Task D is 100% complete, Task Eis 55% complete, and Task F has not started. What is the SPI for the project at the end of the third week? 14. The ACWP at the end of the second week for the project in Problem 12 is $37,900. Determine the CPI for the project. 15. The ACWP at the end of the third week for the project in Problem 13 is $16,500. Determine the CPI for the project. 16. Determine the total estimated cost at completion and estimated cost to complete for the project in Problem 14 Q, assuming the CPI remains the same through the remainder of the job. 17. Determine the total estimated cost at completion and estimated cost to complete for the project in Problem 150, assuming the CPI remains the same through the remainder of the job