Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Please answer all questions, not just one. Thanks in advance! If the price paid per unit differs from the standard price per unit for direct

Please answer all questions, not just one. Thanks in advance! image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
If the price paid per unit differs from the standard price per unit for direct materials, the variance is a a. price variance b. volume variance c. controllable variance d. variable variance od. variable variance The following data is given for the stringer Company: 944 units Budgeted production Actual production 1,055 units $1.9 Materials: Standard price per ounce Standard ounces per completed unit Actual ounces purchased and used in producti Actual price paid for materials 12 13,040 $26,732 Labor: $14.50 per hour Standard hourly labor rate Standard hours allowed per completed unit Actual labor hours worked 5.0 5,433.25 $82,857 Actual total labor costs Overhead: Actual and budgeted fixed overhead Standard variable overhead rate Actual variable overhead costs Overhead is applied on standard labor hours. $1,154,000 $24.00 per standard labor hour $152,131 The direct materials quantity variance is The following data relate to direct labor costs for the current period: Standard costs 7,300 hours at $11.00 Actual costs 6,000 hours at $10.30 What is the direct labor time variance? a. $14,300 unfavorable b. $13,390 favorable c. $13,390 unfavorable d. $14,300 favorable The following data relate to direct labor costs for the current period: Standard costs Actual costs 7,100 hours at $11.20 6,400 hours at $10.40 What is the direct labor rate variance? a. $12,960 unfavorable b. $5,120 favorable c. $12,960 favorable d. $7,840 favorable The Flapjack Corporation had 7,720 actual direct labor hours at an actual rate of $12.34 per hour. Original production had been budgeted for 1.100 units, but only 965 units were actually produced, Labor standards were 7.3 hours per completed unit at a standard rate of $12.75 per hour Round your answer to the nearest cent. The labor time variance is $3,134.32 unfavorable $3,134.32 favorable $8,612.63 unfavorable $8,612.63 favorable The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.96; actual, $2.03 Standard yards per unit: standard, 4.64 yards; actual, 5.23 yards Units of production: 9,500 Calculate the direct materials price variance. a. $3,085.60 favorable b. $3,477.95 favorable c. $3,477.95 unfavorable d. $665.00 unfavorable The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.96; actual, $2.04 Standard yards per unit: standard, 4.60 yards; actual, 5.06 yards Units of production: 9,100 Calculate the direct materials quantity variance. a. $8,539.44 favorable b. $8,204.56 unfavorable Oc. $8,204.56 favorable d. $8,539.44 unfavorable The formula to compute the direct labor rate variance is to calculate the difference between Oa. (Actual labor cost) - (Standard hours x Standard rate) Ob. (Actual labor cost) - (Actual hours x Standard rate) Oc. (Standard hours x Standard rate) - (Standard labor cost) Od. (Standard hours x Actual rate) - (Standard labor cost) The formula to compute the direct materials price variance is to calculate the difference between a. (Actual material cost) - (Standard price x Actual quantity) Ob. (Actual price x Standard quantity) - (Standard material cost) c. (Standard price x Standard quantity) - (Standard material cost) Od. (Actual material cost) - (Standard price x Standard quantity) The standard costs and actual costs for factory overhead for the manufacture of 2,900 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.70 per hour Variable overhead 3 hours per unit @ $2.07 per hour Actual Costs Total variable cost, $17,900 Total fixed cost, $8,000 The amount of the fixed factory overhead volume variance a. $728 unfavorable b. $0 c. $728 favorable d. $910 unfavorable The following data is given for the Bahia Company: Budgeted production 1,079 units 907 units Actual production Materials: Standard price per pound Standard pounds per completed unit $1.772 10 Actual pounds purchased and used in production 8,798 Actual price paid for materials $18,036 Labor: $14.13 per hour Standard hourly labor rate Standard hours allowed per completed unit Actual labor hours worked 4.5 4,671.05 Actual total labor costs $71,234 Overhead: Actual and budgeted fixed overhead $1,045,000 Standard variable overhead rate Actual variable overhead costs Overhead is applied on standard labor hours. $24.00 per standard labor hour $130,789 The variable factory overhead controllable variance is

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions

Question

Give two examples of a structure trade.

Answered: 1 week ago