Please Answer and show work neatly for a better understanding Thank you The budgeted cost for Task A is $25,000, for B is $18,000 and
Please Answer and show work neatly for a better understanding Thank you
The budgeted cost for Task A is $25,000, for B is $18,000 and for Task C is $16,000. Actual costs at the end of the second week of the project indicate that in fact Task A is $26,000, for B is $17,000 and for Task C is $16,500. CPI was previously calculated to be 0.97. Determine the Total Estimated Cost at Completion and cost to complete. Total estimated cost at Completion is $60,340 and Total Cost to Complete is $1,830 Total estimated cost at Completion is $61,340 and Total Cost to Complete is $1,830 Total estimated cost at Completion is $59,500 and Total Cost to Complete is $1,840 a) Total estimated cost at Completion is $60,825 and Total Cost to Complete is $1,325
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started