Question
PLEASE ANSWER BOTH QUESTIONS AND SHOW YOUR EVERY STEP. Baileys standard labor cost of producing one unit of Product DD is 1.7 hours at a
PLEASE ANSWER BOTH QUESTIONS AND SHOW YOUR EVERY STEP.
Baileys standard labor cost of producing one unit of Product DD is 1.7 hours at a rate of $11.3 per hour. During August, 1,452 hours were incurred at a cost of $12.1 per hour to produce 1,111 units of Product DD.
Baileys direct labor rate variance is $__________
11.3 - 12.1 = -0.8 x 1452 = 1161U is wrong
----------------------------------------------------------------
Baileys standard labor cost of producing one unit of Product DD is 1.6 hours at a rate of $10.4 per hour. During August, 1,560 hours were incurred at a cost of $12.8 per hour to produce 1,261 units of Product DD.
Baileys direct labor efficiency variance is $__________
1560 - 1261 x 1.6 = -457.6 x 10.4 = 4759F is wrong
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started