Please answer the following questions using information provided here. Please be aware that the figures are AOA. If AOA bothers you too much, use the
Please answer the following questions using information provided here.
Please be aware that the figures are AOA. If AOA bothers you too much, use the duration and precedence information presented in the diagram to structure your own PDM.
1. TE and TL for the node between activity C and activity D are:_, _
Enter the 2 values separated by a comma and space - for example 3, 2
2. TE and TL for the node beginning activity J are:
3. The total slack for activity K is:
4. TE and TL for the node between activity B and activity G are:_,
5. The length of the critical path is:
6. Suppose you are asked to trim one day from the project. Which task do you trim?
7. The total slack for activity J is:
TE=4 TE= TE=9 TE=12 TL=4 TL= TL=9 O B=4 G=1 TL=12 C K=3 TE=4 Q TE=0 TL=0 A=4 TL=4 O- TE=4 TE=8 TL=5 TL=9 TE=8 TE=11 TE=12 TE=16 TE=0 O E=4 TL=9 TL=12 TL=12 TL=16 OF=3 M=4 TL=0 TE=8 O O TL=9 TE=0 TE= Q TE=6 TL=3 TE= TL= TL=9 TL= TE=10 C=3 D=3 C TL=12 . X = 3 indicates task X requires 3 days of work Please be aware that the figures are AOA. If AOA bothers you too much, use the duration and precedence information presented in the diagram to structure your own PDMStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started