Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Please correctly go through the questions. They're all linked to each other Please make sure to draw the network and the forward pass!! Please!! 3)

Please correctly go through the questions. They're all linked to each other

Please make sure to draw the network and the forward pass!! Please!!image text in transcribed

3) [30 points] Activities' optimistic (a), most likely (m), and pessimistic (b) times in weeks for a small project are shown in the table below: a. [10 points] Draw the network and show the forward pass. b. [4 points] What is the probability of completing the project in 33 weeks or less? c. [4 points] Calculate the number of weeks to complete the project based on a 42% probability. d. [4 points] What is the % of risk associated with an assumed completion time of 28 weeks? e. [4 points] What is the optimistic completion time for the project? f. [4 points] What is the pessimistic completion time for the project

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting A Global Approach

Authors: Sidney J. Gray, Belverd E. Needles

1st Edition

9780395839867

More Books

Students also viewed these Accounting questions

Question

5. Explain how to conduct an appraisal feedback interview.

Answered: 1 week ago

Question

2. Answer the question, Who should do the appraising?

Answered: 1 week ago