Please do not copy-paste answers given by others. Problem 4 Assume you have a project with ten activities labeled A through J. Derive the earliest

Please do not copy-paste answers given by others.

Problem 4

Assume you have a project with ten activities labeled A through J. Derive the earliest expected completion time (TE), latest expected completion time (TL), and slack for each of the tasks (begin at time = 0).

A) Complete the missing values in the table

B) Draw a network diagram and show the critical path

Activity Preceding event Duration TE TL Slack Critical Path?
A 4
B A 5
C A 6
D A 7
E A, D 6
F C, E 5
G D, E 4
H E 3
I F, G 4
J H, I 5

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Databases questions