Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

*PLEASE ENSURE THE EXCEL FORMULA MATCHES THE NUMBERS BELOW* Perot Corporation is developing a new CPU chip based on a new type of technology. Its

*PLEASE ENSURE THE EXCEL FORMULA MATCHES THE NUMBERS BELOW*

Perot Corporation is developing a new CPU chip based on a new type of technology. Its new chip, the Patay2 chip, will take two years to develop. However, because other chip manufacturers will be able to copy the technology, it will have a market life of two years after it is introduced. Perot expects to be able to price the chip higher in the first year, and it anticipates a significant production cost reduction after the first year as well. The relevant information for developing and selling the Patay2 is given as follows:

PATAY2 CHIP PRODUCT ESTIMATES
Development cost $ 20,000,000
Pilot testing $ 5,000,000
Debug $ 3,400,000
Ramp-up cost $ 3,000,000
Advance marketing $ 5,800,000
Marketing and support cost $ 1,000,000 per year
Unit production cost year 1 $ 655.00
Unit production cost year 2 $ 545.00
Unit price year 1 $ 820.00
Unit price year 2 $ 650.00
Sales and production volume year 1 250,000
Sales and production volume year 2 150,000
Interest rate 10 %

Assume all cash flows occur at the end of each period.

a. What is the net present value (at the discount rate of 10%) of this project? (Negative value should be indicated by a minus sign. Enter your answer in thousands of dollars. Round your answer to the nearest thousand.)

b. Perots engineers have determined that spending $10 million more on development will allow them to add even more advanced features. Having a more advanced chip will allow them to price the chip $50 higher in both years ($870 for year 1 and $700 for year 2). What is the NPV of the project if this option is implemented? (Negative value should be indicated by a minus sign. Enter your answer in thousands of dollars. Round your answer to the nearest thousand.)

c. If sales are only 200,000 the first year and 100,000 the second year, what would the NPV of the project be? Assume the development costs and sales price are as originally estimated. (Negative value should be indicated by a minus sign. Enter your answer in thousands of dollars. Round your answer to the nearest thousand.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting For OHADA Member States Volume 1

Authors: Michael Forzeh Fossung

1st Edition

3330328037, 978-3330328037

More Books

Students also viewed these Accounting questions

Question

Describe three other types of visual aids.

Answered: 1 week ago