Question

1 Approved Answer

Please follow the excel spreadsheet and show formulas. There are only 3 spots in the debit of the t - account, not 6 . Please

Please follow the excel spreadsheet and show formulas.
There are only 3 spots in the debit of the t-account, not 6. Please explain.
Aggregator Industries does cement pouring jobs for homes and businesses. Below is information related to its Overhead application:
Estimated Overhead Cost $ 240,000
Estimated Direct Labor Hours 29,000
Actual Direct Labor Hours 31,587
Estimated Machine Hours 74,000
Actual Machine Hours 68,541
Depreciation of Mixing Equipment $ 48,000
Depreciation of Pouring Equipment $ 52,000
Fuel for Cement Truck $ 3,900
Factory Supervisor Salaries $ 104,000
Advertising Expense $ 2,850
Rent Expense for Cement Yard $ 23,000
Required:
Determine the Predetermined Overhead Rate if the Cost Driver is Direct Labor Hours.
Calculate the Over/Underapplied Overhead.
Create a journal entry to dispose of the Over/Underapplied Overhead.
Repeat steps 1-3, but with Machine Hours as the Cost Driver.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Cases An Interactive Learning Approach

Authors: Steven M Glover, Douglas F Prawitt

4th Edition

0132423502, 978-0132423502

More Books

Students also viewed these Accounting questions