Question

1 Approved Answer

Please help me answer these questions 1.Product A is assembled from one B assembly, three C assemblies, two D assemblies, and four H components. Each

Please help me answer these questions

1.Product A is assembled from one B assembly, three C assemblies, two D assemblies, and four H components. Each B assembly is made from two F subassemblies. Each C is made from one G component and one H component. Each D assembly is made from two I assemblies and three G components. Each F subassembly is made from three H components. Each I subassembly is made from one H component.

Construct a product structure tree for product A.

Prepare and indented bill of materials for Product A.

2. Complete the MRP schedule for the part below.

Lot size= 1,200+ Safety stock= 300

Lead time= 2 weeks Allocated= 150

On hand= 850

Week

1

2

3

4

5

6

Gross requirements

100

600

400

900

1,350

700

Scheduled receipts

500

Available

Net requirements

Planned order receipts

Planned order releases

3. Complete the MRP schedule for the part below:

Lot size= 2,000+ Safety Stock= 400

Lead time= 1 week Allocated= 300

On hand= 1,300

Week

1

2

3

4

5

6

Gross requirements

1,100

700

1,500

900

1,850

1,400

Scheduled receipts

2,000

Available

Net requirements

Planned order receipts

Planned order releases

4. Given the following product structure tree and inventory information, complete the MRP schedule below.

Level Code

Product Structure Tree

0

1

2

Product A

Week

1 2 3 4 5 6

Lot size =LFL

Gross requirements

120

340

310

530

410

380

Lead time =1

Schedules receipts

275

On hand=650

Available

Safety Stock=100

Net requirements

Allocated=75

Planned order receipts

Planned order releases

Product B

Week

1 2 3 4 5 6

Lot size =LFL

Gross requirements

Lead time =1

Schedules receipts

400

On hand=430

Available

Safety Stock=120

Net requirements

Allocated=80

Planned order receipts

Planned order releases

Product C

Week

1 2 3 4 5 6

Lot size =1500+

Gross requirements

Lead time =2

Schedules receipts

1,500

On hand=460

Available

Safety Stock=140

Net requirements

Allocated=160

Planned order receipts

Planned order releases

Product D

Week

1 2 3 4 5 6

Lot size =1000+

Gross requirements

Lead time =1

Schedules receipts

On hand=1,100

Available

Safety Stock=200

Net requirements

Allocated=60

Planned order receipts

Planned order releases

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions