Please help me solve! Compute the variable overhead efficiency variance, using the following data: Standard labor hours per good unit produced 2 Good units produced
Please help me solve!
Compute the variable overhead efficiency variance, using the following data: Standard labor hours per good unit produced 2 Good units produced 1,000 Actual labor hours used 2,100 Standard variable overhead per standard labor hour $3 Actual variable overhead $6,500 A. $300 favorable. B. $200 unfavorable. c . $200 favorable. o O D. $300 unfavorableStep by Step Solution