Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

PLEASE HELP ME WITH THIS ASSIGNMENT 12 Student instructions: 1. Download the cost baseline template. 2. Use the information below to create a time-scaled network

PLEASE HELP ME WITH THIS ASSIGNMENT 12

image text in transcribedimage text in transcribedimage text in transcribed

Student instructions: 1. Download the cost baseline template. 2. Use the information below to create a time-scaled network diagram ( FS= finish-to-start) honoring all dependencies. Assume early start dates for each work package (WP). Outline or highlight the cells to indicate the duration of each work package. Work package one has been done for you as an example. 3. Use the budget information above to calculate the weekly budget. Assume a linear relationship between time and money. For example, if a work package was three weeks and has a total budget of $3,000, the weekly budget would be $1,000(3$1,000=$3,000). 4. There is one row for every work package. The time-scale is in weeks represented as "W1, W2, etc." for week 1 , week 2 , etc. in the column headers. 5. Calculate the weekly incremental budget for each work package and place it in the correctweek based on dependencies and work package durations. 6. Calculate the project's weekly incremental costs and place the total in the "incremental costs" cell for each week (column). 7. Calculate the project's cumulative budget to-date for each week and place in the "cumulative costs" cell for each week (column). 8. Answer the questions related to the completed assignment. 9. Once complete, submit your assignment as instructed. \begin{tabular}{|l|l|l|l|l|l|l|l|l|l|l|l|l|l|l|l|l|l|l|l|l|} \hline Incremental costs & & & & & & & & & & & & & & & & & & & \\ \hline Cumulative costs & & & & & & & & & & & & & & & & & & & \\ \hline \end{tabular} Total project budget is: Week with highest incremental cost: How many weeks have exactly two work packages planned? At which week does the cumulative budget first exceed $40,000 ? At which week is the incremental budget exactly $4,200 ? Student instructions: 1. Download the cost baseline template. 2. Use the information below to create a time-scaled network diagram ( FS= finish-to-start) honoring all dependencies. Assume early start dates for each work package (WP). Outline or highlight the cells to indicate the duration of each work package. Work package one has been done for you as an example. 3. Use the budget information above to calculate the weekly budget. Assume a linear relationship between time and money. For example, if a work package was three weeks and has a total budget of $3,000, the weekly budget would be $1,000(3$1,000=$3,000). 4. There is one row for every work package. The time-scale is in weeks represented as "W1, W2, etc." for week 1 , week 2 , etc. in the column headers. 5. Calculate the weekly incremental budget for each work package and place it in the correctweek based on dependencies and work package durations. 6. Calculate the project's weekly incremental costs and place the total in the "incremental costs" cell for each week (column). 7. Calculate the project's cumulative budget to-date for each week and place in the "cumulative costs" cell for each week (column). 8. Answer the questions related to the completed assignment. 9. Once complete, submit your assignment as instructed. \begin{tabular}{|l|l|l|l|l|l|l|l|l|l|l|l|l|l|l|l|l|l|l|l|l|} \hline Incremental costs & & & & & & & & & & & & & & & & & & & \\ \hline Cumulative costs & & & & & & & & & & & & & & & & & & & \\ \hline \end{tabular} Total project budget is: Week with highest incremental cost: How many weeks have exactly two work packages planned? At which week does the cumulative budget first exceed $40,000 ? At which week is the incremental budget exactly $4,200

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Global Logistics Delivering The Goods

Authors: John Manners Bell

1st Edition

074947825X, 978-0749478254

More Books

Students also viewed these General Management questions