A project consists of the activities in the following table. Times are given in weeks
Activity | Preceding | Time |
A | 2 | |
B | 3 | |
C | A | 7 |
D | A, B | 3 |
E | C | 4 |
F | D | 6 |
- Draw the network diagram
- Calculate the ES, EF, LS, LF, and slack for each activity
- What is this project completion time?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started