Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: PA3-3 (Algo) Weighted-Average Method [LO 3-2, 3-3] Required: 1. Using the weighted-average method of process costing, complete each of the following steps: a. Reconcile the number of physical units worked on during the period. b. Calculate the number of equivalent units. c. Calculate the cost per equivalent unit. d. Reconcile the total cost of work in process. a. Reconcile the number of physical units worked on during the period. b. Calculate the number of equivalent units. c. Caiculate the cost per equivalent unit. d. Reconcile the total cost of work in process. Complete this question by entering your answers in the tabs below. Using the weighted-average method of process costing, reconcile the number of physical units worked on during the period. Required: 1. Using the weighted-average method of process costing, complete each of the following steps: a. Reconcile the number of physical units worked on during the period. b. Calculate the number of equivalent units. c. Calculate the cost per equivalent unit. d. Reconcile the total cost of work in process. Complete this question by entering your answers in the tabs below. Using the weighted-average method of process costing, calculate the number of equivalent units. PA3-3 (Algo) Weighted-Average Method [LO 3-2, 3-3] Required: 1. Using the weighted-average method of process costing, complete each of the following steps: a. Reconcile the number of physical units worked on during the period. b. Calculate the number of equivalent units. c. Calculate the cost per equivalent unit. d. Reconcile the total cost of work in process. Complete this question by entering your answers in the tabs below. Using the weighted-average method of process costing, calculate the cost per equivalent unit. Note: Round Cost per Equivalent Unit to 5 decimal places. Required: 1. Using the weighted-average method of process costing, complete each of the following steps: a. Reconcile the number of physical units worked on during the period. b. Calculate the number of equivalent units. c. Calculate the cost per equivalent unit. d. Reconcile the total cost of work in process. Complete this question by entering your answers in the tabs below. Using the weighted-average method of process bosting, reconcile the total cost of work in process. Note: Use Cost per Equivalent Unit rounded to 5 decimal places and round your final answers to the nearest dollar amount