Please help The Work Effort is calculated to be 180 days (or 1440 hours) using the Work Effort Calculator and the Staffing Plan for 4
Please help The Work Effort is calculated to be 180 days (or 1440 hours) using the Work Effort Calculator and the Staffing Plan for 4 project resources is showing 1600 hours for 10 week Project Duration. What is the variance in work effort? Is this acceptable? Why or why not? How can this variance be adjusted or corrected