Please I just need E to be answeared with computations. Dalton Construction Co. contracted to build a bridge for $10,000,000. Construction began in 2021 and

Please I just need E to be answeared with computations.

Dalton Construction Co. contracted to build a bridge for $10,000,000. Construction began in 2021 and was completed in 2022. Data relating to the construction are:

2021 2022

Costs incurred during the year $3,300,000 $2,750,000

Estimated costs to complete 2,700,000

Dalton uses the percentage-of-completion method.

Instructions

(a) How much revenue should be reported for 2021? Show your computation.

(b) Make the entry to record progress billings of $4,100,000 during 2021.

(c) Make the entry to record the revenue and gross profit for 2021.

(d) How much gross profit should be reported for 2022? Show your computation.

(e) Compute the gross profit recognized in 2021 and 2022 if the company uses the completed contract method.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Finance For Growing Enterprises

Authors: Edward W. Davis, Roger Buckland

1st Edition

1138679941, 978-1138679948

More Books

Students also viewed these Finance questions