Please I need some help with this project management exercise. Using the project network below, reduce the project duration from 12 days to 8. For

Please I need some help with this project management exercise.

image text in transcribed
Using the project network below, reduce the project duration from 12 days to 8. For each reduction indicate the compressed activities and adjust the total direct costs. Maximum Normal Normal direct No. Slope compression duration cost HAS 50 3 150 B 100 1 3 100 VS 60 2 4 200 D 60 2 3 200 E 70 1 4 200 F 0 1 150 B D Original duration of the project: 12 3 3 HAS F 3 1x VS E Total direct costs: $1000 4 4

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach to Planning Scheduling and Controlling

Authors: Harold Kerzner

10th Edition

978-047027870, 978-0-470-5038, 470278706, 978-0470278703

More Books

Students also viewed these General Management questions

Question

1. How is economics like a science?

Answered: 1 week ago

Question

Explain the various methods of job evaluation

Answered: 1 week ago

Question

Differentiate Personnel Management and Human Resource Management

Answered: 1 week ago

Question

Describe the functions of Human resource management

Answered: 1 week ago

Question

What are the objectives of Human resource planning ?

Answered: 1 week ago