Please Prepare the journal entries for all and calculate the estimated gross profit (a-b) a. Using the percentage-of-completion method, calculate the estimated gross profit that
Please Prepare the journal entries for all and calculate the estimated gross profit (a-b)
a. Using the percentage-of-completion method, calculate the estimated gross profit that would be recognized during each year of the construction period. Round the percent complete to the nearest whole percentage point. b. Using the completed contract method, calculate the estimated gross profit that would be recognized during each year of the construction period. c. Prepare the journal entries for all three years and post to their respective Tee a/c's
PLEASE ANSWER
THNAK YOU
3 Rivera Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.8 million beginning September 1,2022 , to build a road for a municipality. It has been estimated that the road construction will be complete by June 2024 . The following data pertain to the construction periodStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started