Please provide the following for a 3-week deck construction project plan consisting of the following activities in order: 1) design/permits, 17 days 2) Site grading,

Please provide the following for a 3-week deck construction project plan consisting of the following activities in order:

1) design/permits, 17 days

2) Site grading, 4 days

3) Foundation, 3 days

4) Wood framing, 4 days

5) decorate finishes, 4 days

6) electrical, 5 days

7) final clean. 1 days

The cost for the entire project is $5K down & $5K at completion for a total of $10K to be completed in a 3 week time frame.

Please provide the predecessor and successor, develop a network diagram, find the critical path and estimate early start, early finish, and slack time for all activities in days.

Thanks

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Coping With Financial Accounting 1 For Senior Secondary Schools And Undergraduate Studies

Authors: Festus Chukwunwendu Akpotohwo ,Stella Alfred-Jaja Wellington-Igonibo ,Cletus Ogeibiri

1st Edition

3659611034, 978-3659611032

More Books

Students also viewed these Accounting questions

Question

Define personal and dependency exemptions.

Answered: 1 week ago