Please provide the following for a 3-week deck construction project plan consisting of the following activities in order: 1) design/permits, 17 days 2) Site grading,
Please provide the following for a 3-week deck construction project plan consisting of the following activities in order:
1) design/permits, 17 days
2) Site grading, 4 days
3) Foundation, 3 days
4) Wood framing, 4 days
5) decorate finishes, 4 days
6) electrical, 5 days
7) final clean. 1 days
The cost for the entire project is $5K down & $5K at completion for a total of $10K to be completed in a 3 week time frame.
Please provide the predecessor and successor, develop a network diagram, find the critical path and estimate early start, early finish, and slack time for all activities in days.
Thanks
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started