PLEASE SHOW EXCEL FORMULAS AND SOLVER CONSTRAINTS Tip: To address the stipulation that that at least two of the projects 1, 3, 5, 6 must
PLEASE SHOW EXCEL FORMULAS AND SOLVER CONSTRAINTS
Tip: To address the stipulation that that at least two of the projects 1, 3, 5, 6 must be undertaken, make Sum of B12, D12, F12, G12 >= 2
To address the stipulation that Project 4 cannot be undertaken unless both projects 1 & 3 are also undertaken make E12 Real Estate Project Selection. Brooks Development Corporation (BDC) faces the following capital budgeting decision. Six real estate projects are available for investment. The net present value and expenditures required for each project (in millions of dollars) are as follows: There are conditions that limit the investment alternatives: - At least two of projects 1,3,5, and 6 must be undertaken. - If either project 3 or 5 is undertaken, they must both be undertaken. - Project 4 cannot be undertaken unless both projects 1 and 3 also are undertaken. The budget for this investment period is $220 million. a. Formulate a binary integer program that will enable BDC to find the projects to invest in to maximize net present value, while satisfying all project restrictions and not exceeding the budget. b. Solve the model formulated in part (a). What is the optimal net present value? Which projects will be undertaken? How much of the budget is unused? creenshot 2023-10-19 at... Real Estate Project Selection. Brooks Development Corporation (BDC) faces the following capital budgeting decision. Six real estate projects are available for investment. The net present value and expenditures required for each project (in millions of dollars) are as follows: There are conditions that limit the investment alternatives: - At least two of projects 1,3,5, and 6 must be undertaken. - If either project 3 or 5 is undertaken, they must both be undertaken. - Project 4 cannot be undertaken unless both projects 1 and 3 also are undertaken. The budget for this investment period is $220 million. a. Formulate a binary integer program that will enable BDC to find the projects to invest in to maximize net present value, while satisfying all project restrictions and not exceeding the budget. b. Solve the model formulated in part (a). What is the optimal net present value? Which projects will be undertaken? How much of the budget is unused? creenshot 2023-10-19 at
Step by Step Solution
There are 3 Steps involved in it
Step: 1
To solve this problem using Excels Solver follow these steps Step by Step Instructions 1 Enter the D...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started