Question

1 Approved Answer

Please type responses if possible or if you need to write it, please make sure it is legible and easy to follow. If you are

Please type responses if possible or if you need to write it, please make sure it is legible and easy to follow. If you are not sure of your responses, please just leave blank.

1.) The higher the cost slope of an activity the lower the cost to reduce its duration.

  • True
  • False

2.) Indirect costs generally represent overhead costs such as supervision, administration, consultants, and interest.

  • True
  • False

3.) Total cost for specific project durations is computed and then compared with the benefits of reducing project time, before the project begins or while it is in progress.

  • True
  • False

4.) Brooks' law states that adding manpower to a software project helps keep it on schedule

  • True
  • False

5.) A construction contractor finished a bridge across a river 12 months early and received more than $5 million for the early completion. This is an example of reducing project duration caused by

  • imposed project deadlines.
  • time to market
  • unforeseen project delays
  • high overhead
  • incentive contracts

6.) When adding resources, there are limits as to how much speed can be gained

  • True
  • False

7.) If indirect costs are a significant percentage of total project costs, reductions in project time can represent very real savings

  • True
  • False

8.) Direct costs are so named because they can be assigned directly to a work package and activity.

  • True
  • False

9.) Without any formal planning, the president of a high-tech company remarks in a speech that new technologically advanced routers will be available in one year. This may lead to a project that must be done faster than anticipated. This is an example of reducing project duration caused by

  • imposed project deadlines.
  • time to market
  • unforeseen project delays
  • high overhead
  • incentive contracts

10.) Incentive contracts can make the reduction of project time rewardingusually for both the project contractor and owner.

  • True
  • False

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality Business Development

Authors: Ahmed Hassanien, Crispin Dale

2nd Edition

1351033689, 9781351033688

More Books

Students also viewed these General Management questions