Question
1 Approved Answer
pls help me 3. Using the following job log, calculate all of the basic project measures (BAC, PV, EV, and AC) and the progress indicators
pls help me
3. Using the following job log, calculate all of the basic project measures (BAC, PV, EV, and AC) and the progress indicators (SPI, CPI, SV, CV, and EAC). Is the project on schedule? Assume that it is currently 01-Nov-20. [10M) (C03] Actual effort Task Estimated/Planned effort Estimated completion date Actual completion date 1 40 60 15-Aug-20 10-Sep-20 2 2 25 20 20-Sep-20 20-Sep-20 3 20 40 30-Sep-20 01-Oct-20 4 30 30 13-Nov-20 01-Nov-20 5 60 02-Dec-20 6 80 25-jan-21Step by Step Solution