plz assist Achi 122 EF tinc LS LF #D ES EF-ES+t LS LFT 11-13 Sid Davidson was able to determine the activity times for the
plz assist
Achi 122 EF tinc LS LF #D ES EF-ES+t LS LFT 11-13 Sid Davidson was able to determine the activity times for the leadership training program. He would like to determine the total project completion time and the critical path(s). The activity times appear in the following table (see Problem 11-12) Stast finish ACTIVITY TIME (DAYS) 2 5 1 Slack LS-ES LF-EF D E F G 10 3 6 35 Step by Step Solution